How are the railways, roads and public transport doing?

Short answer: Nine out of ten passenger trains arrived on time in 2025, but the 95 per cent target has never been met, and only seven out of ten long-distance trains were on time. The railway has a maintenance backlog of around 90 billion kronor, and the interlockings are 37 years old on average. The national plan for 2026 to 2037 totals 1,171 billion kronor, just over half of it for new roads and lines such as Ostlänken and Norrbotniabanan. A monthly pass for the whole county costs from 1,010 kronor on Gotland to just over 3,000 kronor in Norrbotten. 203 people died on the roads in 2025, the lowest number since the Second World War and the lowest in the EU per inhabitant.

More on travel and ownership: Privatisation shows what happened when the trains and other services were opened to competition, Electric cars works out charging and costs, Sweden's environmental impact shows the emissions and Water and sewage what it costs to repair the pipes under the streets. How far it is to a health centre, school and shop in towns and in the countryside is on Rural and urban, and how well fibre and the mobile network reach Digitalisation and broadband.

Punctuality

How many trains arrive on time.

Share of passenger trains that reached their final station no more than five minutes behind the timetable, excluding Saltsjöbanan and Roslagsbanan. Of trains run counts only trains that actually ran; of trains planned counts every train in the plan the day before, and a cancelled train then counts as late. Source: Trafikanalys, official statistics from 2013.

In 2013 Trafikverket and the rail industry agreed that 95 per cent of all trains would be on time by 2020. It was never reached. The best year was 2020 itself, with 94.9 per cent, a year when the pandemic meant fewer trains ran. Since then the share fell to 87.1 per cent in 2024, about as low as 2010, the worst year since 2001 according to Trafikverket. In 2025 it turned upwards again. Riksrevisionen, the National Audit Office, has pointed out that nobody has calculated what reaching 95 per cent would cost or whether it is worth it.

In 2019, 32 per cent of delays were caused by the train operators themselves, 18 per cent by faults in track, signals and power, and 12 per cent by traffic control, according to Riksrevisionen. Among infrastructure faults, signalling, track and power systems were the most common causes. People on the tracks delayed more than 10,000 trains in 2025.

The maintenance debt

The maintenance that has been put off.

When a track, a switch or a bridge is not maintained in time, a debt builds up that eventually has to be paid, in delays or in costlier repairs. Trafikverket estimates the railway's maintenance backlog at around 90 billion kronor. The plan is for it to shrink by 10 to 15 per cent by 2037 and be gone by 2050. On the roads the backlog is to be gone as early as 2037.

The need has grown fast. The groundwork for the 2026 to 2037 plan puts the cost of keeping the railway in working order at 76 billion kronor, 30.5 billion or 67 per cent more than for the previous plan. Power systems and signalling account for most of the increase. The roads need 29.4 billion, 20 per cent more, according to Trafikanalys.

  1. The interlockings

    The interlockings that control signals and switches are 37 years old on average and have 12 years of technical life left. The oldest tenth are 63 years old.

    Trafikverket, the state of the network

  2. Track and switches

    Trafikverket's 14,200 kilometres of track are 28 years old on average and its 10,600 switches 29 years. The overhead line masts are 59 years old on average.

    Trafikverket, the state of the network

  3. Money for maintenance

    Trafikverket spent about 10 billion kronor on railway maintenance in 2021 and just over 18 billion in 2026.

    Trafikverket, how we catch up

  4. The network

    The railway has 10,903 kilometres of line in service and 15,776 kilometres of track. 2,099 kilometres are double track or more, 75 per cent is electrified and the new ERTMS signalling system covers 787 kilometres.

    Trafikanalys, Rail traffic 2025

The national plan

What is being built until 2037 and what it costs.

On 24 April 2026 the government adopted the national transport infrastructure plan for 2026 to 2037. The frame is 1,171 billion kronor in 2025 prices, 21 per cent more than the previous plan. 607 billion goes to new roads and lines, 354 billion to operating and maintaining the roads and 210 billion to operating and maintaining the railway. Funding for road maintenance rises by 53 per cent and for rail by 18 per cent. On top of the frame, about 91 billion comes from track charges, congestion tax and municipalities and regions that help pay.

Big projects often end up costing more than planned. In 2021 Riksrevisionen found that costs for the projects it examined had risen by 39 per cent on average over four years, 58 billion kronor in total.

The largest projects in the plan, estimated cost, length and when they open.
ProjectCostLengthOpens
Ostlänken, Järna to LinköpingSEK 102.8 bn150 km2035 to Norrköping
Norrbotniabanan, Umeå to LuleåSEK 62 bn270 km2036 to Skellefteå
Västlänken, tunnel under GothenburgSEK 36.5 bn8 km2030
ERTMS, new signalling systemSEK 29.3 bn in the planwhole countryin stages
Hässleholm to Lund, two new tracksSEK 6.6 bn in the planno dataafter 2037

Costs for Ostlänken and Norrbotniabanan are Trafikverket's in 2025 prices, for Västlänken in current prices; in 2009 Västlänken was estimated at 25.7 billion. For ERTMS and Hässleholm to Lund only the amount set aside in the 2026 to 2037 plan is given. Sources: government communication 2025/26:259 and Trafikverket's project pages.

Deregulation

From one state-owned SJ to fifteen train operators.

Sweden was one of the first countries in Europe to separate the tracks from the trains. In 1988 Banverket took over the tracks and SJ remained as the train operator. Freight was opened to competition in 1996, and from 2010 any operator could run passenger trains on commercial terms, in practice from the 2012 timetable. The regions procure their own regional trains.

Since 1990 the number of train departures has risen by about 150 per cent and travel has more than tripled. The cheapest fare on the high-speed trains has fallen by around 65 per cent since 1996, while the most expensive has risen by 30 per cent, according to Transportstyrelsen. In 2024 there were 15 passenger operators in eight groups, and the SJ group had 66 per cent of turnover. How deregulation has affected prices, punctuality and ownership more broadly is described on the page on privatisation.

Public transport

What a monthly pass costs in your county.

    Monthly pass for 28 to 31 days valid across the whole county, adult, full fare, in kronor. Prices are from August 2026 according to HurBra, for Halland and Västerbotten from January according to Carup. The sources differ for Kronoberg (1,551 kronor in January), Gotland (883), Gävleborg (1,869) and Norrbotten (2,860). From 1 July to 31 December 2026 the state pays half the price in every county.

    A county pass in Norrbotten costs almost three times as much as in Stockholm, because the county is large and journeys are long. In the big cities passes are cheap relative to how much they are used. SL's pass has still become 54 per cent more expensive since 2010, and according to SCB local transport prices rose by 139 per cent from 2000 to 2022, against 32 per cent for prices overall. Örebro, Västmanland, Dalarna and Västernorrland, on the other hand, have cheaper county passes today than in 2014.

    Road safety

    How many are killed and injured on the roads.

    Number killed in road traffic accidents per year from Transportstyrelsen's accident statistics. The series breaks in 2010, when suicides stopped being counted; that explains part of the drop that year.

    In 1997 the Riksdag adopted Vision Zero: that nobody should be killed or seriously injured in traffic, and that roads and vehicles should be built so that human mistakes are not fatal. Since then deaths have fallen from 541 to 203 a year, by 62 per cent, while traffic has grown. Median barriers on 2+1 roads, speed cameras, safer cars and lower speeds in built-up areas are some of the reasons.

    The government's target is no more than 133 deaths in traffic in 2030 and a quarter fewer seriously injured. In May 2026 Trafikverket judged that Sweden is not on track to meet the target. With 20 deaths per million inhabitants in 2025, Sweden still had the lowest death rate in the EU, ahead of Denmark with 23.

    Sources and method

    Where the figures come from.

    Punctuality comes from the Trafikanalys API, the rest is compiled from the sources.